History, Projects and Milestones

Mercier, Quebec, Canada

La Tuque, Quebec, Canada

1917     Sir Adam Beck, Ontario (formerly Queenston Chippawa): 
              Largest power station in the world at the time

2000     Voith and Siemens merge their hydro power activities

2003     Mercier, Quebec: 
              Supply and installation of 5 groups - 5 x 10.5 MW 
              Kaplan Saxo Turbines and 200 RPM Generator

2004     La Tuque, Quebec: 
              Upgrade and installation of 3 groups - 3 x 55 MW 
              Francis Turbines and Generators rated at 65 mVA

2006     Revelstoke U5, British Columbia:
              Supply and installation of one group - 1 x 512 MW
              vertical Francis turbine and one umbrella type generator
              rated at 532 mVA

2007     Eastmain 1A, Quebec:
              Supply and installation of 3 groups - 3 x 260 MW 
              vertical Francis turbines and Generators